Retainage
Last updated October 1, 2026
Retainage, also called retention or a holdback, is a share of each progress payment that is kept back until a construction project is finished. It gives the payer leverage to make sure the work is completed properly and that everyone down the line gets paid.
Retainage shows up at several levels. A project owner holds it from the general contractor. The general contractor holds it from subcontractors. And a construction lender often holds back part of each construction draw under its loan agreement. The OCC (Office of the Comptroller of the Currency), which supervises national banks in the US, notes that under a progress payment plan, banks commonly hold back 10 to 20 percent of each payment to cover overruns or unpaid bills.
The math is simple: retainage held = approved draw × retainage rate. Here is an example with round, hypothetical numbers. An approved draw of $200,000 at 10 percent retainage funds $180,000 and holds $20,000. After five similar draws, $100,000 is held. Some contracts lower the rate once the job is half done, and most release the balance at substantial or final completion.
Why it matters for lenders
Retainage is a cushion. If a contractor walks off the job or a subcontractor files a lien, the held money can pay to finish the work or settle the claim. Releasing it too early removes that cushion when the project is most exposed.
The rules vary by state, so lenders shouldn't assume one standard. In the US, some states cap retainage or set deadlines for releasing it, and the rules can differ for public and private projects. For example, for most private contracts signed on or after January 1, 2026, California caps retainage at 5 percent, with some exceptions. A lender's own holdback is set by its loan agreement, but it has to work alongside the owner's contracts and the law where the project sits. Lenders should confirm local rules with counsel.
How it works in practice
A loan administrator funds monthly draws on a 40-unit apartment project. With each draw, she records the retainage held by budget line and by contractor. At substantial completion, the borrower asks for a partial release. She confirms the inspector's completion report, collects lien waivers and checks title before releasing part of the balance. At final completion, she requires final waivers from every trade, the final inspection, and a certificate of occupancy before releasing the rest.
In a side spreadsheet, retainage totals drift from the loan balance. That turns the final draw on a construction loan into the slowest and riskiest one.
Related terms
Construction Draw
A construction draw is a payment from a construction loan, released after the borrower asks for money for completed work and the lender confirms it. Each draw is checked against the project budget, supported by an inspection and lien waivers, reduced by any retainage, and then added to the loan balance.
Construction Loan
A construction loan is short-term financing for building or substantially rebuilding a property. Instead of paying out the full amount at closing, the lender releases money in stages, called draws, as work is completed and verified. Borrowers usually pay interest only on the amount drawn, and the loan is repaid by a sale or a permanent loan.
Lien Waiver
A lien waiver is a signed document in which a contractor, subcontractor or supplier gives up some or all of its right to file a lien on a property, usually in exchange for payment. Construction lenders collect lien waivers with draws to confirm the people doing the work were paid and to protect the lender's own lien.
Interest Reserve
An interest reserve is money set aside within a construction or bridge loan to pay the loan's interest while a project is being built or leased up and isn't yet earning income. The lender pays interest from the reserve each month, so the loan stays current until the project produces cash. Regulators warn it can hide a failing project.
Loan Disbursement
The release of loan money by the lender, either to the borrower or to others on the borrower's behalf, such as a seller, a title company, a prior lender or a contractor. A loan may be paid out all at once at closing or in stages, as with construction draws and line of credit advances. Each release needs checks and approvals before money moves.
Further reading
See how lenders put this into practice
FUNDINGO runs origination, servicing and reporting on one loan record inside Salesforce.